Post move… !

After the inevitable moving day chaos, the kitchen had been turned into a general temporary dumping...

Moving day!

It’s arrived! With enough of the house ready to move into, we decided the time had come to get...

Bathroom… Done!

Just in time for our planned moving in date, and after many late nights the first bathroom was...

Bathroom 8

We’re definitely on the home straight with this room now. The ceiling’s been painted, and...

Bathroom – 7

Kicking off by partially draining down the heating system again, the pipework was quickly checked...

Bathroom – 6

An evening of grouting later, the floor’s looking like it’s finished – and most importantly, is nearly...

Bathroom build …. 5

Tiling’s well underway, and with all the wall tiles firmly in place we made a start on the...

With all the prep work completed, the time had finally come to make a start on tiling. Tiles were...

Bathroom build 3

With the ceiling boarding complete, we started taping & jointing the boards to provide a (hopefully)...

Bathroom build…2

With  the tray installed, waste pipework installed & tested & floor screwed firmly down we were able...

Bathroom build

With the flooring prepared, joists strengthened & route prepared for the waste pipework; the first...

With the subfloor up to spec, next stop was to cut & lay the new plywood flooring ready for test...

New bathroom floor

Given the state of the old floor boards in the bathroom we were left with little option except to...

Kitchen – the reveal!

All building work’s now been completed and the kitchen is finished (bar a tiled...

Bathroom floors

Once the old bathroom had been stripped out we were able to get our first good look at the...